Completed before any change to a task, procedure, service level, staffing model, apparatus, equipment, PPE, facility, substance, supplier, contractor, operational software or organizational structure takes effect, as Policy - Risk Management and Hazard Assessment section 5.5 requires. Management of change is a required element of the management-system standard (ISO 45001:2018, cl. 8.1.3) and a core component of safety assurance in the aviation safety management model this management system draws on (ICAO, 2016, Annex 19). The applicable regulation may require a written procedure to be updated when conditions change, reviewed with affected persons before work starts and developed in consultation with the committee, and may require the employer to consult the committee when establishing or reviewing any written policy, procedure, plan or code of practice (J06 Written Procedures and Committee Consultation); this checklist does all of these for every change. Opened by the change initiator’s program manager; the hazard and control sections follow the method in 03 Hazard Profile and Risk Register Method (CSA Z1002:12); filed with the program’s records and logged in the quarterly management of change log.
| Field |
Entry |
| Change identifier |
|
| Title of the change |
|
| Initiator (role) and program |
|
| Date raised |
|
| Type: permanent, or temporary with end date |
|
| Category (one or more): task; procedure or SWP; service level or declared service; staffing or deployment model; apparatus; equipment or tool; PPE; facility; substance or product; supplier or contractor; operational software or system; organizational structure; other |
|
| Description of the change: what is changing, from what, to what |
|
| Reason for the change (hazard, standard or regulation, learning review recommendation, audit finding, equipment end of life, service demand, cost, member proposal) |
|
| Source documents (learning review, trial report, research review, JOHSC recommendation, regulator order) |
|
| Field |
Entry |
| Stations, divisions, platoons affected (career and volunteer stated separately) |
|
| Roles affected |
|
| Members needing training before the change |
|
| Mutual aid partners, contractors, dispatch or other agencies affected |
|
| Other programs and teams affected (joint session held, date) |
|
Part C: Hazards and controls
#
| Field |
Entry |
| Learning-team session held with the members who do the task (date, facilitator) or reason it was not needed |
|
| Hazards introduced by the change |
|
| Hazards removed by the change |
|
| Hazards altered (frequency, severity, who is exposed) |
|
| Risk assessment reference (register entry number, date, assessor) |
|
| Risk rating before and after controls |
|
| Controls, in hierarchy order: elimination; substitution; engineering; administrative; PPE |
|
| Where a lower-level control is chosen while a higher one is practicable, the reason |
|
| Residual risk accepted by (role), date |
|
| Emergency and contingency provisions affected (mayday, rescue, exposure, evacuation) |
|
Part D: Documents and records to change
#
| Document |
Change needed (new, revise, retire) |
Owner |
Due date |
Done |
| Policy |
|
|
|
|
| Program module |
|
|
|
|
| Safe work procedure(s) |
|
|
|
|
| Training outline and competency sign-off |
|
|
|
|
| Forms, checklists, inspection records |
|
|
|
|
| Equipment standards list and apparatus manifest |
|
|
|
|
| Risk register entry |
|
|
|
|
| Capability matrix (where a declared service changes) |
|
|
|
|
| Mutual aid agreement or contract |
|
|
|
|
Part E: Consultation and gates
#
| Field |
Entry |
| JOHSC standing consultant involved (name of role, date) |
|
| Safety-sensitive (new or changed safety-sensitive equipment, PPE, policy, SOG or SWP with safety content, or safety-sensitive training): yes or no, with reason |
|
| If safety-sensitive: formal JOHSC consultation sent (date), response received (date), disposition and the department’s decision |
|
| Equipment Standards, Apparatus and PPE gate: request logged (date), disposition (date) |
|
| {{Union}} and {{Volunteer Association}} consulted where the collective agreement or practice requires (dates) |
|
| Clinician consulted where medical or respiratory implications (date) |
|
| Counsel consulted where legal implications (date) |
|
| Field trial required: evaluation trial or procurement trial; report reference |
|
Part F: Training and communication
#
| Field |
Entry |
| Training required before the change takes effect (who, what, hours, by when) |
|
| Training delivered and recorded (date, learning management system reference) |
|
| Change notice issued to every affected station (date; the team lead to ask) |
|
| Read at start of shift and at volunteer training nights (confirmation by station, dates) |
|
| Members who raised the issue told what was decided and why (date) |
|
Part G: Approval and effective date
#
| Field |
Entry |
| Program manager: approved, signature, date |
|
| Deputy chief: approved where safety-sensitive or crossing programs, signature, date |
|
| Fire chief: approved where a policy, a declared service or an organizational structure changes, signature, date |
|
| Effective date |
|
| End date (temporary change) and who will confirm reversal |
|
Part H: Post-change review
#
| Field |
Entry |
| Review date (default 90 days after the effective date, or the next quarterly update) |
|
| Works as done? Learning-team check-in or station round findings |
|
| Indicators or events since the change (near misses, reports, inspection findings) |
|
| Residual actions logged in the Corrective Action Register (numbers) |
|
| Change closed (role, date) or returned to Part C |
|
| Field |
Type |
Required |
Who completes |
| Change identifier |
Text, unique |
Yes |
Program manager or system |
| Title, initiator, program, date raised |
Text and date |
Yes |
Initiator |
| Type and end date |
Choice and date |
Yes; end date for temporary changes |
Initiator |
| Category |
Multiple choice |
Yes |
Initiator |
| Description and reason |
Text |
Yes |
Initiator |
| Source documents |
References |
Where applicable |
Initiator |
| Part B rows |
Text |
Yes, every row (none where none) |
Program manager |
| Learning-team session |
Date and facilitator, or reason |
Yes |
Team lead |
| Hazards introduced, removed, altered |
Text |
Yes, every row |
Team with the health and safety officer |
| Risk assessment reference and ratings |
Reference and ratings |
Yes |
Assessor |
| Controls by hierarchy |
Text per level |
Yes |
Team |
| Reason for a lower-level control |
Text |
Yes where applicable |
Program manager |
| Residual risk accepted by |
Role and date |
Yes |
Program manager (deputy chief where high) |
| Emergency provisions |
Text |
Yes |
Team |
| Part D rows |
Choice, owner, date, done |
Every row (not applicable where none) |
Program manager |
| Part E rows |
Dates, choices, dispositions |
Yes; formal JOHSC consultation mandatory where safety-sensitive |
Program manager; JOHSC consultant |
| Part F rows |
Text and dates |
Yes |
Training officer; team lead |
| Part G approvals |
Signatures and dates |
Program manager always; others as stated |
As stated |
| Effective and end dates |
Dates |
Yes |
Program manager |
| Part H review |
Text and dates |
Yes |
Team lead; program manager closes |
Retention. With the program’s records for the life of the change plus 10 years; the quarterly management of change log goes to the senior team and to the JOHSC for information (Policy - Records, Privacy and Health Information). Privacy. Roles, not names; the learning-team write-up attached names no individuals.
Jurisdiction requirements
#
This chapter relies on the following legal requirements, which differ by province and territory. Check your jurisdiction’s section on each topic page before adopting it.
| Topic |
What to check in your jurisdiction |
Page |
| Joint Committee and Health and Safety Representative |
The committee’s statutory functions, including advising on PPE and on policies and programs (Part E) |
J05 Joint Committee and Health and Safety Representative |
| Written Procedures and Committee Consultation |
When written procedures are required and the rules for updating them when conditions change, reviewing them with affected workers before work starts and keeping them at the work area; and the duty to consult the committee on written policies, procedures, plans and codes of practice (Parts D, E and F) |
J06 Written Procedures and Committee Consultation |
| Equipment Inspection, Ladders and Aerial Devices |
The inspection required for new or changed equipment before use and by a competent person at set intervals, and how long inspection records must be kept (Part D) |
J15 Equipment Inspection, Ladders and Aerial Devices |
International Civil Aviation Organization [ICAO]. (2016). Annex 19 to the Convention on International Civil Aviation: Safety management (2nd ed.).
International Organization for Standardization. (2018). ISO 45001:2018, Occupational health and safety management systems: Requirements with guidance for use. https://www.iso.org/standard/63787.html